An application for a Certificate of lawfulness of Existing Use on land  on School Lane has been submitted to Cheshire East Planning Department. As you may have noticed the development to build two dwellings and a car park on a strip of land along the side of School Lane and between it and the cricket  pitch has been on hold for some time. It is not clear why but the letter clearly indicates a concern by the developers that they may now or soon  be in breach on planning conditions.

The original application (15/0198N) was granted on appeal in October 2015 with the condition that development be started within three years. This is a standard condition for all developments and is a means of trying to get work done in a reasonable period. Clearly some basic work has begun. Footings have been begun and access through the hedge has been created. However, work has been on hold for some weeks. The applicant is asking Cheshire East planning department to agree that they have complied with the start condition and issue the Certificate of Lawfulness of Existing use of Land to ensure that action cannot be taken against them for noncompliance. The implication being that the project will be on hold now until after the latest permitted start date (October 2018).

These certificates or CLEUD ‘s are therefore designed to ensure that enforcement of planning conditions cannot  or should not proceed. It protects the developer from such enforcement or the possibility that the original planning permission is withdrawn. There are, as I understand the law, minimum time periods for eligibility on the development. The breach of planning must be continuous and current and the application must be based on evidence. The time period is 4 years. Does that mean the applicant is intending to keep the  development on hold for a further year or more?

Update:

The Certificate has now been granted by Cheshire East and we can expect a period of delay of up to 2 years.

 

 

 

 

 

 

 

 

 